Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A,
FEP-09/364/2009/B and FEP-10/364/2009/B Monthly Environmental Monitoring & Audit Report
- february 2014 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
12 March 2014 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects
under this Project
Table
2.2 Details of Individual Contracts
under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Table
3.5 Summary of submission status
under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Table
3.7 Summary of submission status
under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Table
3.9 Summary of submission status
under FEP-05/364/2009/A
Table
3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/15
Table
3.11 Summary of submission status
under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13 Summary
of submission status under FEP-07/364/2009/A
Table
3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under FEP-08/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.17 Summary of submission status under FEP-09/364/2009/B
Table 3.18 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.19 Summary of submission status under
FEP-10/364/2009/B
Table 4.1 Noise Monitoring
Stations
Table
4.2 Real Time Noise Monitoring
Stations
Table
4.3 Air Monitoring Stations
Table
5.1 Noise Monitoring Stations for
Contract no. HY/2009/18
Table
5.2 Noise Monitoring Station for
Contract no HK/2009/01 and HK/2009/02
Table
5.3 Noise Monitoring Stations for
Contract no. HY/2009/15
Table
5.4 Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table
5.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Table
5.9 Air Monitoring Stations for
Contract no. HY/2009/18
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air Monitoring Station for Contract no. HY/2009/15
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table
5.15 Details of Waste Disposal for
Contract no. HK/2009/01
Table
5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for
Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for
Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for
Contract no. HK/2010/06
Table 5.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.22 Details of Waste Disposal for Contract no. HY/2010/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.4
Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table
8.7 Summary of Environmental Inspections for
Contract no. HY/2010/08
Table 8.8 Summary of Environmental Inspections for Contract no. HY/2010/08
Table
9.1 Cumulative Statistics on
Complaints
Table
9.2 Cumulative Statistics on
Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
The installation of pre-bored H-piles in CWB stage 2 Atrium Link
¡P
The installation of pre-bored H-piles in CWB stage 3 Atrium Link
¡P
Demolition of P5 Pump house at Promenade Deck
¡P
Installation of ELS at first layer for Stage 1.
¡P
Installation of ELS at second layer.
¡P
Pumping test for CWB Tunnel Structure Works at Stage 1
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Construction of OHVD base slab at Eastbound and upper side wall at
Westbound
¡P
Mobilization of D-Wall plant at WCR2 area for remaining D-Wall
construction at the Southern side along the existing seawall cope line.
¡P
Guide wall and ground treatment for remaining D-Wall construction at
Portion 2.
¡P
D-wall construction was commenced on 4 Feb 14.
¡P
Concreting of D-wall Panel
¡P
Casting of Bored Pile Nos. PN30
¡P
Installation of Bored Pile Nos. PC32
¡P
Preparation works for D-wall construction at Panel Nos. P144 ¡V P146
¡P
Casting of guide wall and the pre-grouting works.
¡P
Preparation works for D-wall construction at Panel Nos. C
¡P
Preparation works for D-wall construction at Panel Nos. P147 ¡V P154
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Tunnel construction at TS2, TS4 & TPCWAE
¡P
Dismantling of struts at TS4 & TPCWAE
¡P
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
¡P
Mined tunnel lining construction
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal of strut at ELS
¡P
Construction of Pile cap, column and cross-head (Land)
¡P
Removal of marine platform
¡P
Construction of cross head (Marine)
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Installation of dewatering well
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building commenced
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Installation of protection layer for
precast unit
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
¡P Site preparation works
¡P Site survey
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Demarcation of graphics,
¡P
Erection of noise absorption sheeting,
¡P
Pipe pile & pre-boring works,
¡P
Re-provisional of turtle pond &
¡P
Loop detector installation works.
Noise
Monitoring
Air Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Drainage works
¡P Tunnel works including scaffolding
erection, excavation, OHVD installation, roadside barriers, top and base slab
construction, extract sheet pile, waterproofing and backfill
¡P Trough structure construction and
associated drilling and grouting
¡P Road works
¡P Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
¡P Preparation works for the new temporary
road at Expo Drive East
¡P Temporary utilities diversion at the new
reclaimed area
¡P Installation of pre-bored H-piles at 4th
row & ED (total 38 nos. piles)
¡P Remaining D-wall construction at tunnel
south (13 nos. panels)
¡P Excavation for stage 1 down to -10 mPD
¡P Tunnel structure works
¡P Base slab construction at Bay 5.
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P Complete all tunnel structure.
¡P Pre-grouting and guide wall at TWCR4
area.
¡P Bored pile construction those in the
vicinity of Bridge 1 & 2 under Hung Hing Road Flyover Diversion (Stage 2)
and continue others bored pile construction at Tunnel Portion 3 & 4.
¡P Mini-piling works for foundation of
Bridge 3 under Hung Hing Road Flyover Diversion (Stage 2) and complete
mini-pile loading test at pile no. M
¡P Concrete deck and steel deck on existing
Box Culvert O Bay 17 ¡V Bay 19.
¡P Mobilization for D-Wall construction at
Tunnel Portion 3 & 4 and complete the preparation works for D-wall
construction at Panel Nos. C
¡P Existing
¡P D-wall construction along Hung Hing Road
slow lane.
¡P D-wall construction at Tunnel Portion 6.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P Tunnel construction at TS2, TS4 &
TPCWAE
¡P Dismantling of struts at TS4 &
TPCWAE
¡P Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal.
¡P Mined tunnel lining construction
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at Watson Road
¡P Bored piling (Land)
¡P Removal of strut at ELS
¡P Construction of Pile cap, column and
cross-head (Land)
¡P Removal of marine platform
¡P Construction of Dolphin Cap
¡P ELS, EVB and Cut & Cover Tunnel
¡P Installation of dewatering well
¡P Laying of 1500f pipe
¡P Launching of segments
¡P Extraction of temporary pile from marine
section
¡P Construction of bridge TA1
¡P Pre-bored H-pile for Admin. Building
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Repair and installation of slotted
panels
¡P Installation of protection layer for
precast unit
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
¡P Site preparation works
¡P Site survey
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P Tree & root pruning works
¡P Tree removal works,
¡P Tree transplanting works,
¡P Tree works within off-site nursery
compound,
¡P Drainage improvement works,
¡P Sheet piling works,
¡P Demarcation of graphics,
¡P Pipe pile & pre-boring works,
¡P Re-provisional of turtle pond,
¡P Loop detector installation works &
¡P UMP installation works.
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009B during the period January 2014 to February 2014. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V summarizes
the status of valid Environmental Permits / Licenses during the reporting
period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table
2.1 Schedule 2 Designated
Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater
intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of
Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Frank
So |
9103
2370 |
|||
Environmental
Supervisor |
Mr. Stanley Chan |
9047 6148 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Desmond Sze |
2214
7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Donald Ip |
2214
7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Dorothy Shing |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms. Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Eric Yip |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew
TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor
WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul
LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching
Man, CHAN |
6050
4919 |
|||
|
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
|
|
Site
Agent |
Dr. Dave
Chan |
3467
4277 |
|
Environmental
Officer |
Mr. C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
The installation of pre-bored H-piles in CWB stage 2 Atrium Link
¡P
The installation of pre-bored H-piles in CWB stage 3 Atrium Link
¡P
Demolition of P5 Pump house at Promenade Deck
¡P
Installation of ELS at first layer for Stage 1.
¡P
Installation of ELS at second layer.
¡P
Pumping test for CWB Tunnel Structure Works at Stage 1
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction of OHVD base slab at Eastbound and upper side wall at
Westbound
¡P
Mobilization of D-Wall plant at WCR2 area for remaining D-Wall construction
at the Southern side along the existing seawall cope line.
¡P
Guide wall and ground treatment for remaining D-Wall construction at
Portion 2.
¡P
D-wall construction was commenced on 4 Feb 14.
¡P
Concreting of D-wall Panel
¡P
Casting of Bored Pile Nos. PN30
¡P
Installation of Bored Pile Nos. PC32
¡P
Preparation works for D-wall construction at Panel Nos. P144 ¡V P146
¡P
Casting of guide wall and the pre-grouting works.
¡P
Preparation works for D-wall construction at Panel Nos. C
¡P
Preparation works for D-wall construction at Panel Nos. P147 ¡V P154
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Tunnel construction at TS2, TS4 & TPCWAE
¡P
Dismantling of struts at TS4 & TPCWAE
¡P
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
¡P
Mined tunnel lining construction
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal of strut at ELS
¡P
Construction of Pile cap, column and cross-head (Land)
¡P
Removal of marine platform
¡P
Construction of cross head (Marine)
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Installation of dewatering well
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building commenced
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
¡P
Installation of protection layer for precast unit
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Site preparation works
¡P
Site survey
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Demarcation of graphics,
¡P
Erection of noise absorption sheeting,
¡P
Pipe pile & pre-boring works,
¡P
Re-provisional of turtle pond &
¡P
Loop detector installation works.
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
¡P
Excavation of trial pit
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD installation,
roadside barriers, top and base slab construction, extract sheet pile,
waterproofing and backfill
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Preparation works for the new temporary road at Expo Drive East
¡P
Temporary utilities diversion at the new reclaimed area
¡P
Installation of pre-bored H-piles at 4th row & ED (total 38 nos.
piles)
¡P
Remaining D-wall construction at tunnel south (13 nos. panels)
¡P
Excavation for stage 1 down to -10 mPD
¡P
Tunnel structure works
¡P
Base slab construction at Bay 5.
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Complete all tunnel structure.
¡P
Pre-grouting and guide wall at TWCR4 area.
¡P
Bored pile construction those in the vicinity of Bridge 1 & 2 under
Hung Hing Road Flyover Diversion (Stage 2) and continue others bored pile
construction at Tunnel Portion 3 & 4.
¡P
Mini-piling works for foundation of Bridge 3 under Hung Hing Road
Flyover Diversion (Stage 2) and complete mini-pile loading test at pile no. M
¡P
Concrete deck and steel deck on existing Box Culvert O Bay 17 ¡V Bay 19.
¡P
Mobilization for D-Wall construction at Tunnel Portion 3 & 4 and
complete the preparation works for D-wall construction at Panel Nos. C
¡P
Existing
¡P
D-wall construction along Hung Hing Road slow lane.
¡P
D-wall construction at Tunnel Portion 6.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Tunnel construction at TS2, TS4 & TPCWAE
¡P
Dismantling of struts at TS4 & TPCWAE
¡P
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
¡P
Mined tunnel lining construction
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal of strut at ELS
¡P
Construction of Pile cap, column and cross-head (Land)
¡P
Removal of marine platform
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Installation of dewatering well
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
¡P
Repair and installation of slotted panels
¡P
Installation of protection layer for precast unit
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P
Site preparation works
¡P
Site survey
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree removal works,
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Demarcation of graphics,
¡P
Pipe pile & pre-boring works,
¡P
Re-provisional of turtle pond,
¡P
Loop detector installation works &
¡P
UMP installation works.
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP was surrendered by the Contractor on 25
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
3.1.5.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table
3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Table 3.5 Summary of submission
status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition
2.7 & 2.8 |
Works
Schedule and Location Plan |
18 May
2011 |
Condition
2.6 |
Environmental
Management Organization Chart |
18 May
2011 |
Condition
2.6 |
Commencement
Date of Works |
20 Jun 2011 |
Condition
2.9 |
Noise
Management Plan |
10
Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.1) |
31 Oct 2013 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS0857-13 |
2 Aug
2013 |
15 Aug
2013 to 14 Feb 2014 |
Expired |
GW-RS1078-13 |
30 Sep
2013 |
18 Oct
2013 to 17 Apr 2014 |
Valid |
|
GW-RS1119-13 |
11 Oct
2013 |
16 Oct
2013 to 15 Apr 2014 |
Valid |
|
GW-RS1128-13 |
8 Oct
2013 |
11 Oct
2013 to 6 Apr 2014 |
Valid |
|
GW-RS0945-13 |
29 Aug 2013 |
11 Sep 2013
to 10 Mar 2014 |
Valid |
|
GW-RS0993-13 |
6 Sep 2013 |
20 Sep 2013
to 19 Mar 2014 |
Valid |
|
GW-RS1027-13 |
10 Sep 2013 |
15 Sep 2013
to 09 Mar 2014 |
Valid |
|
GW-RS1002-13 |
12Sep 2013 |
25 Sep 2013
to 24 Mar 2014 |
Valid |
|
GW-RS1197-13 |
4 Nov 2013 |
10 Nov 2014
to 9 May 2014 |
Valid |
|
GW-RS1254-13 |
12 Nov 2013 |
17 Nov 2013
to 16 May 2014 |
Valid |
|
GW-RS1256-13 |
12 Nov 2013 |
22 Nov 2013
to 21 May 2014 |
Valid |
|
GW-RS1240-13 |
7 Nov
2013 |
28 Nov 2013
to 27 May 2014 |
Valid |
|
GW-RE1199-13 |
6 Nov 2013 |
30 Nov 2013
to 29 May 2014 |
Valid |
|
GW-RS1258-13 |
12 Nov 2013 |
17Nov 2013
to 06 May 2014 |
Valid |
|
GW-RS1261-13 |
12 Nov 2013 |
13 Nov 2013
to 06 May2014 |
Valid |
|
GW-RS1325-13 |
27 Nov 2013 |
30 Nov 2013
to 29 May 2014 |
Valid |
|
GW-RS1337-13 |
27 Nov 2013 |
29 Nov 2013
to 26 May 2014 |
Valid |
|
GW-RS1466-13 |
24 Dec
2013 |
17 Jan
2014 to 16 July 2014 |
Valid |
|
GW-RS1458-13 |
24 Dec
2013 |
2 Jan
2014 to |
Valid |
|
GW-RS0067-14 |
29 Jan
2014 |
15 Feb
2014 to |
Valid |
|
GW-RS0112-14 |
13 Feb
2014 |
16 Feb
2014 to |
Valid |
|
Discharge
Licenses |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Cancelled |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 |
30 |
Valid |
|
WT00009691-2011 |
1 Aug
2011 |
31 July
2016 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-01/364/2009
EP
Condition |
Submission |
Date of Submission |
Condition
2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition
2.6 |
Environmental Management
Organization Chart |
14 Jun
2011 |
Condition
2.6 |
Commencement Date of Works |
21 Jun
2011 |
Condition 2.11 |
Landscape
Plan (Revision B) |
20 Nov 2012 |
Condition
2.9 |
Noise Management
Plan (Revision A) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and Permits
under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification
of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1145-13 |
15 Oct 2013 |
04 Nov 2013 ¡V |
Valid |
GW-RS1302-13 |
15 Nov 2013 |
18 Nov 2013 ¡V |
Valid |
|
GW-RS1285-13 |
12 Nov 2013 |
14 Nov 2013¡V 07 May 2014 |
Valid |
|
GW-RS0820-13 |
19 July 2013 |
03 Aug 2013 to 02 Feb 2014 |
Expired |
|
GW-RS1118-13 |
04 Oct 2013 |
22 Oct 2013 to 21 Apr 2014 |
Cancelled |
|
GW-RS0053-14 |
21 Jan 2014 |
03 Feb 2014 to 01 Aug 2014 |
Valid |
|
Discharge
Licence |
WT00012998-2012 |
25 May 2012 |
31 Jan 2016 |
Valid |
WT00013967-2012 |
17 Sep 2012 |
30 Sep 2017 |
Valid |
|
WT00014966-2013 |
08 Jan 2013 |
31 Jan
2018 |
Valid |
|
Registration
as a Waste Producer |
WPN:
8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration
completed |
Billing Account under Waste Disposal Ordinance
(Land) |
Account
No.: 7011587 |
11 Oct 2010 |
Account
approved |
Valid |
Table 3.9 Summary of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date
of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 5) |
12 March 2012 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1243-13 |
7 Nov 2013 |
09 Nov 2013 to 03 May 2014 |
Valid |
GW-RS0882-13 |
12 Aug 2013 |
14 Aug 2013 to 13 Feb 2014 |
Cancelled |
|
GW-RS0106-14 |
14 Feb 2014 |
16 Feb 2014 to 9 Aug 2014 |
Valid |
|
GW-RS1105-13 |
8 Oct
2013 |
10 Oct
2013 to 6 Apr
2014 |
Valid |
|
GW-RS1384-13 |
3 Dec
2013 |
4 Dec
2013 to 27 May 2014 |
Valid |
|
GW-RS1437-13 |
17 Dec
2013 |
31 Dec
2013 to 30 Jun 2014 |
Valid |
|
GW-RS1491-13 |
27 Dec
2013 |
2 Jan
2014 to 30 Jun 2014 |
Valid |
|
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance (Dumping by Vessel) |
7011761 |
25 Sep 2013 |
17 Oct 2013 to 16 Jan 2014 |
Valid |
Water Discharge License (TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Valid |
Water Discharge License
(Discharge at CHT area) |
WT00012941-2012 |
10 May 2012 |
10 May 2012 to 31 May 2014 |
Valid |
Water Discharge License
(Discharge at TS4) |
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012 to 31 Jan 2014 |
Expired |
Water Discharge License
(Discharge at TS2 |
WT00014974-2013 |
10 Jan 2013 |
10 Jan 2013 to 31 Jan
2015 |
Valid |
Water Discharge License (Discharge
at TPCWAE) |
WT00018167-2014 |
17 Jan 2014 |
17 Jan 2014 to 31 Dec 2015 |
Valid |
Table 3.11 Summary of submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
11 Mar
2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works
Schedule |
15 Mar
2011 |
Condition 2.8 |
Location
Plan |
15 Mar
2011 |
Condition 2.9 |
Noise
Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape Plan |
19 Oct 2011 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table
3.13
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10 Feb
2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar
2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21 July
2011 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
GW-RS1473-13 |
29 Dec
2013 |
29 Dec 2013 to 23 Jun 2014 |
Valid |
GW-RS1176-13 |
25 Oct
2013 |
25 Oct 2013 to 22 Apr 2014 |
Cancelled |
|
GW-RS0072-14 |
04 Feb 2014 |
06-Feb-14
to 02-Aug-14 |
Cancelled |
|
GW-RS0073-14 |
04 Feb 2014 |
06-Feb-14
to 02-Aug-14 |
Valid |
|
GW-RS1009-13 |
06 Sept
2013 |
09 Sep 0213 to 08 Mar 2014 |
Cancelled |
|
GW-RS1099-13 |
08 Oct 0213 |
21 Oct
2013 to 20 Apr 2014 |
Valid |
|
GW-RS1179-13 |
25 Oct 2013 |
22 Oct 2013 to 22 Apr 2014 |
Cancelled |
|
GW-RS1474-13 |
27 Dec 2013 |
29 Dec 2013 to 23 Jun 2014 |
Valid |
|
Dumping
Permit (Tunnel) (Type 1 ¡V Open Sea Disposal) |
EP/MD/14-128 |
30 Jan 2014 |
30 Jan 2014 to 30 Jun 2014 |
Valid |
Dumping Permit (Tunnel) (Type 1 ¡V
Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/14-116 |
20 Jan 2014 |
20 Jan 2014 to 19 Feb 2014 |
Expired |
Dumping Permit (Tunnel) (Type 1 ¡V
Open Sea Disposal) |
EP/MD/14-104 |
10 Dec 2013 |
10 Dec 2014 to |
Valid |
Dumping Permit (Tunnel) (Type 1 ¡V
Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal |
EP/MD/14-127 |
20 Feb 2014 |
20 Feb 2014 to 19 Mar 2014 |
Valid |
Water
Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Cancelled |
WT00010093-2011 |
17-Aug-12 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13 Summary of submission status under
FEP-07/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.13 |
Landscape Plan (Rev.2) |
29 July 2012 |
Condition 2.9 |
Noise Management Plan (Rev.3) |
15
March 2013 |
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
3.1.10.
The current status on licences and/or permits on environmental protection
pertinent and submission under FEP-08/364/2009/A for contract no. HK/2010/06 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-08/364/2009/A |
15
June 2012 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
GW-RS-924-13 |
21 Aug
2013 |
27 Aug
2013 ¡V 26 Feb 2014 |
Expired |
GW-RS1435-13 |
19 Dec
2013 |
23 Dec
2013 ¡V 30 Mar 2014 |
Valid |
Table 3.15 Summary of submission status under
FEP-08/364/2009
EP Condition |
Submission |
Date
of
Submission |
|
Acknowledgement letter of FEP-08/364/2009A |
14
Aug 2012 |
Condition 2.9 |
Noise Management Plan |
26 Nov 2012 |
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West
3.1.11
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-09/264/2009/B for contract no.
HK/2012/08 showed in Table 3.16 and Table 3.17
Table 3.16 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March
2013 |
N/A |
Valid |
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb
2013 |
18 Jul
2017 |
Valid |
Table 3.17 Summary of submission status under FEP-09/364/2009
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management Plan (Rev.2) |
9 July
2013 |
Condition 2.14 |
Landscape Plan (Rev.1) |
30 May
2013 |
Contract no. HY/2010/08 ¡VCentral ¡V
Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)
3.1.12 The current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-09/264/2009/B for contract no. HK/2012/08 showed in Table 3.18 and Table 3.19
Table 3.18 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-10/364/2009/B |
2013-07-26 |
NA |
Valid |
Notification
of Works Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing
Account under Waste Disposal Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Valid |
Construction
Noise Permit (CNP) for non-pilling works |
GW-RS1363-13 |
2013-12-02 |
2013-12-10
to 2014-06-09 |
Valid |
GW-RS1376-13 |
2013-12-03 |
2013-12-09 to 2014-06-02 |
Valid |
|
GW-RS0971-13 |
2013-09-04 |
2013-09-04
to 2014-03-03 |
Cancelled |
|
GW-RS1017-13 |
2013-09-10 |
2013-09-15
to 2014-03-09 |
Cancelled |
|
GW-RS1089-13 |
2013-09-30 |
2013-10-02 to 2014-04-01 |
Cancelled |
|
GW-RS0094-14 |
2014-02.-11 |
16 Feb
2014 to 16 Jul 2014 |
Valid |
|
Construction
Noise Permit (CNP) for pilling works |
PP-RS0032-13 |
2013-12.-20 |
2 Jan
2014 to 30 Jun 2014 |
Valid |
Table 3.19 Summary of submission status under FEP-10/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.1) |
20 August 2013 |
Noise
Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to
M8 for City Hall
* Remark 2: M7e has become a reference station
starting from 7 Aug 2012
Real time Noise Monitoring
Stations
4.1.2.
Review of feasibility on the real time noise
monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan
fireboat Station was found not appropriate to be a monitoring station for
monitoring the IECL Piling works and Demolition after visited.
4.1.3.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu |
Tin Hau |
RTN4 |
|
Noise
Monitoring Parameters, Frequency and Duration
4.1.4.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.5.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.6.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
¡P One set of measurements between 0700
and 1900 hours on normal weekdays.
¡P One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
¡P One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.7.
If construction works are extended to include
works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring
Equipment
4.1.8.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.9.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.10.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit. Measurements
will be accepted as valid only if the calibration level from before and after
the noise measurement agree to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil
Street Site Office** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as ¡§Oil Street Site Office¡¨
in April 2013.
Air Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
¡P 0.6 ¡V 1.7 m3 per minute
adjustable flow range;
¡P Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
¡P Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
¡P Capable of providing a minimum exposed
area of 406 cm2;
¡P Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
¡P Equipped with a shelter to protect the
filter and sampler;
¡P Incorporated with an electronic mass
flow rate controller or other equivalent devices;
¡P Equipped with a flow recorder for
continuous monitoring;
¡P Provided with a peaked roof inlet;
¡P Incorporated with a manometer;
¡P Able to hold and seal the filter paper
to the sampler housing at horizontal position;
¡P Easily changeable filter; and
¡P Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8¡¨ x 10¡¨ shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange
Contract no.
HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no.
HY/2010/08 ¡V Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass over MTR
Tsuen Wan Line
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
West
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline
noise level was performed from 11
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.1.2 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.1 below:
Table
5.1
Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark:
M7e has become a reference station starting from 7 Aug 2012
5.1.3 No action or limit level exceedance was
recorded in this reporting month.
5.1.4
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.2 below.
Table
5.2
Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6
No action or limit level exceedance was
recorded in this reporting month.
5.1.7
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
5.1.8 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.3 below.
Table
5.3 Noise Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.9
No action or limit level exceedance was
recorded in this reporting month.
5.1.10
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.11 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table
5.4
Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.12
Three limit level
exceedances were recorded on 13, 20 and 25 February 2014 at M6 ¡V HK Baptist Church Henrietta
Secondary School in the reporting month.
5.1.13
Major traffic noise observed during
monitoring on 13, 20 and 25
February 2014 and it was
considered as the major noise contribution. As such, the limit level exceedances
were concluded as non-project related.
5.1.14
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 ¡V
Central-Wanchai Bypass ¡VWanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.1.15 The commencement
of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02
September 2013. The proposed divisions of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.16
No action or limit level exceedance was
recorded in this reporting month.
5.1.17
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
As confirmed by CWB RSS, the IECL parapet removal operations and
associated construction work will commence in June 2013. Liaison was conducted with HK Baptist
Church Henrietta Secondary School, Po Leung Kuk Yu Lee Mo Fan Memorial School and
Causeway Bay Community Centre regarding the set up of RTN3 real time noise monitoring
station.
5.2.2.
5.2.3.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013.
5.2.4.
Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up
on 4 Sep 2012 and station set up was performed on 14 Sep 2012. Real time noise
baseline capturing was conducted during time period without construction work
from 21 Sep 2012 to 04 Oct 2012.
5.2.5.
Real time noise monitoring at RTN3 ¡V Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced
since 06 Oct 2012.
5.2.6.
Oil Street Community Liaison Centre was confirmed to be demolished in
mid-October by CWB RSS. This
presented a need for relocation of RTN2 ¡V Oil Street Community Liaison
Centre. After liaison with Hong
Kong Electric, permission was granted on 21 Sep 2012 for real time noise
monitoring set up at City Garden Electric Centre (RTN2a ¡V Electric Centre),
which is a representative of the noise sensitive receiver City Garden.
5.2.7.
RTN2 previously located at oil Street Community Liaison Centre was
relocated to Hong Kong Electric Centre on 5 Oct 2012, which is a representative
of the noise sensitive
5.2.8.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.2.9.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table
5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu |
RTN4 |
Tin
Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
5.2.10.
Limit level exceedances were recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot during restricted hours on 1 Feb
2014 in the reporting month. After checking with contractor, no major noisy
construction activities were conducted at the concerned location during the
recorded period. As such, the exceedances were considered as non-project
related and contributed by the Chinese New Year pyrotechnic display.
5.2.11.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 29 January 2014 and 18 February 2014
and during restricted hours on 1 and 18 February 2014. After checking with contractor, no noisy
construction activities were conducted at the concerned location during daytime
on 29 January 2014 and 18 February 2014 and no construction activities were
conducted at the concerned location during restricted hours on 1 February 2014
and 18 February 2014. As the exceedances were non-continuous, the exceedances
were considered as non-project related and contributed by nearby IEC traffic
and nearby non-CWB Project.
5.2.12.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 28 January 2014. After
checking with contractor, no major noisy construction activities were conducted
at the concerned location during the recorded period. As such, the exceedance
were considered as non-project related and contributed by nearby IEC traffic.
5.2.13.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 1 February 2014 in
the reporting month. After checking with contractor, no major noisy
construction activities were conducted at the concerned location by the
Contractor during the recorded period. As such, the exceedances were considered
as non-project related and contributed by Chinese New year pyrotechnic display.
5.2.14.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2009/18 ¡V
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.3.1
Air monitoring for the Central Interchange
works under contract no. HY/2009/18 was commenced on 21
Table 5.9
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
5.3.2
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air monitoring results and graphical
presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
5.3.3
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 5.10 below.
Table
5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
5.3.4
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.5
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table
5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.6
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
5.3.7
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table
5.12 below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.8
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.3.9
The proposed division of air monitoring
stations are summarized in Table 5.13 below. Air monitoring for
the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.
Table
5.13
Air Monitoring
Stations
for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
|
5.3.10
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
5.4.1.
Inert C&D wastes and non-inert C&D wastes were disposed in this
reporting month. Details of the waste flow table are summarized in
Table 5.15.
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed |
78.4 |
53202.985 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
10104.5 |
N/A |
Non-inert C&D materials disposed |
4.28 |
1535.33 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
Nil |
10350 |
N/A |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.16.
Table 5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
2324.975 |
255541.662 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
Nil |
18161 |
n/a |
Non-inert C&D materials disposed, m3 |
37.293 |
1344.993 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
12071 |
SENT Landfill |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HY/2009/18
547 |
103084 |
||
101 |
56574 |
||
81 |
1879 |
||
0.03 |
82.48 |
||
Nil |
4440 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month(m3) |
Cumulative Quantity-to-Date(m3) |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
194.39 64.29 |
489774.99 242937.71 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
271828.5 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan |
Non-inert C&D
materials disposed, m3 |
102.42 |
1603.38 |
SENT Landfill |
Non-inert C&D
materials recycled, m3 |
800 |
547054.2 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
21955 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 ¡V Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
6662.62 |
473080.69 |
N/A |
Inert
C&D materials recycled |
Nil |
62104.43 |
N/A |
Non-inert
C&D materials disposed |
15.34 |
1091.17 |
SENT Landfill |
Non-inert
C&D materials recycled |
5.63 |
352.04 |
N/A |
Chemical
waste disposed |
0.13 |
5.96 |
N/A |
Dumping
Permit (Tunnel) (Type-1 Open Sea Disposal), m3 |
2034 |
2961 |
South of Cheung Chau |
Marine
Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 ¡V
Confined Marine Disposal), m3 |
3462 |
10730 |
East of Sha Chau |
Contract no.
HK/2010/06 Wan Chai Development Phase II - Central-Wan Chai Bypass over MTR
Tsuen Wan Line under FEP-08/364/2009/A
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
12.5 |
303.6 |
SENT |
Non-inert C&D materials recycled |
NIL |
5070 |
Recyclers |
Chemical waste disposed |
Nil |
0.2 |
N/A |
Contract no. HK/2012/08 Wan Chai
Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21 Details of Waste
Disposal for Contract no. HK/2012/08
Waste Type* |
Quantity this month, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
Nil |
Nil |
N/A |
Inert
C&D materials recycled |
Nil |
Nil |
N/A |
Non-inert
C&D materials disposed |
Nil |
Nil |
N/A |
Non-inert
C&D materials recycled |
Nil |
Nil |
N/A |
Chemical
waste disposed |
Nil |
Nil |
N/A |
C
Contract no. HY/2010/08
Central
¡V Wan Chai Bypass (CWB) ¡V Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Waste Type* |
Quantity this month, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
747 31 |
3044.4 69.029 |
TM 38 TKO area 137 |
Inert C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D materials disposed |
42 |
341 |
SENT |
Non-inert C&D materials recycled |
Nil |
Nil |
Nil |
Chemical waste disposed |
30 |
60 |
Nil |
Table 5.22 Details of Waste Disposal for
Contract no. HY/2010/08
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.1.1. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
6.1.2. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.3. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
6.1.4. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.5.
Three limit level
exceedances were recorded on 13, 20 and 25 February 2014 at M6 ¡V HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 13, 20 and 25 February 2014, traffic noise
was major contribution in the noise monitoring and exceedances were not related to the
Project.
Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.6. No exceedance
was recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.8. Limit level
exceedances were recorded at RTN2a-Electric Centre during daytime on 29 January
2014 and 18 February 2014 and during restricted hours on 1 and 18 February
2014. After checking with
contractor, no noisy construction activities were conducted at the concerned
location during daytime on 29 January 2014 and 18 February 2014 and no
construction activities were conducted at the concerned location during
restricted hours on 1 February 2014 and 18 February 2014. As the exceedances
were non-continuous, the exceedances were considered as non-project related and
contributed by nearby IEC traffic and nearby non-CWB Project.
6.1.9. Limit level
exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School during daytime
on 28 January 2014. After checking with contractor, no major noisy construction
activities were conducted at the concerned location during the recorded period.
As such, the exceedance were considered as non-project related and contributed
by nearby IEC traffic.
6.1.10. Limit level
exceedances were recorded at RTN4-Causeway Bay Community Centre during
restricted hours on 1 February 2014 in the reporting month. After checking with
contractor, no major noisy construction activities were conducted at the
concerned location by the Contractor during the recorded period. As such, the
exceedances were considered as non-project related and contributed by Chinese
New year pyrotechnic display.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
6.2.2.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.3.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceedance was recorded in the reporting
month.
6.3.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance from
monitoring was recorded in the reporting month.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/B, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Monthly EM&A report
(January 2014) of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
minor modification works at completed footpath and at Road P2/D7 pedestrian
crossing were performed in February 2014 reporting month. The water
quality monitoring was completed in October 2011 and no Project-related exceedance
was recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was insignificant.
7.0.3. According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II were marine works at
HKCEC areas, cross-harbour Watermains, Fresh Watermains and Cooling Watermains
Installations, tunnel works at Wan Chai East. The major construction activities
under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were tunnel construction at TS4 and tunnel construction and dismantling of
struts at TPCWAE. Bridge construction and tunnel works at Central Interchange, ELS
segment launching works and tunnel works at North Point area. The major environmental impact was water quality
impact at
7.0.4.
The major environmental impacts generated
from tunnel works at Central and tunnel works at Wan Chai East, IECL and
Causeway Bay Typhoon Shelter were undertaken in the reporting month. No
significant air impact from construction activities was anticipated in the
reporting month. Besides, no project-related exceedances were recorded during
the air and noise environmental monitoring events in the reporting month. Thus,
it is evaluated that the cumulative construction impact from the concurrent
projects including Wan Chai Development Phase II was insignificant.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and
HK/2010/06. No non-conformance was identified during the site audits. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
8.0.2.
Four site inspections for Contract no.
HY/2009/15 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
140204_02 |
4-Feb-14 |
Clear the
leaked oil as chemical waste and provide proper maintenance to machinery
(TS4) |
The leaked
oil was cleared as chemical waste. |
Completion
as observed on 11 Feb 2014 |
140211_01 |
11-Feb-14 |
Improve
the oil connection point to prevent leakage and clear the leaked oil as
chemical waste |
Oil
connection point have been improved |
Completion
as observed on 18 Feb 2014 |
140218_01 |
18-Feb-14 |
Provide
embankment protection near surface collection point leading to public drain |
Embankment
protection have been provided. |
Completion
as observed on 5 March 2014 |
140225_01 |
25-Feb-14 |
Leaked oil
should be cleared as chemical waste (TS2) |
Leaked oil
was cleared as chemical waste. |
Completion
as observed on 4 March 2014 |
140225_02 |
25-Feb-14 |
Silt
Curtain should be properly deployed to enclose the works area for filling
works at EVA (TS1) |
The
condition of silt curtain deployed have been improved |
Completion
as observed on 4 March 2014 |
140225_03 |
25-Feb-14 |
Clear the
floating scum and removed the damaged silt curtain to prevent entrapment of
scum (TS4/ Ex-PCWA) |
Floating
scum have been removed |
Completion
as observed on 4 March 2014 |
8.0.3.
Four site inspections for Contract no.
HY/2009/18 was carried out during this reporting period. No observation was found in the reporting
month.
8.0.4.
Four site inspections for Contract no.
HY/2009/19 was carried out during this reporting period. No observation was
found in the reporting month.
8.0.5.
Four site inspections for Contract no.
HK/2009/01 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.4
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/01
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
1400212_01 |
12-Feb-14 |
Water
should be treated prior to discharge ( Bay 8 &9 ) |
Water was
directed to sedimentation tank prior to discharge |
Completion
as observed on 26 Feb 2014 |
140220_01 |
20-Feb-14 |
Stockpile
should be properly covered or sprayed with water more frequently ( Water
Channel , Bay8 ) |
Covering
was provided |
Completion
as observed on 26 Feb 2014 |
140220_02 |
20-Feb-14 |
Oil spill
was observed, excavator should be properly maintained to prevent oil spill
(Bay8 ) |
The
excavator with oil spill was removed |
Completion
as observed on 26 Feb 2014 |
140220_03 |
20-Feb-14 |
Drip tray
should be properly plugged to prevent spillage of oil. ( Expo drive East) |
Plug was
provided |
Completion
as observed on 26 Feb 2014 |
140226_01 |
26-Feb-14 |
Oil should
be prevented from dropping on the ground. ( Expo Drive East ) |
The
excavator with oil spill was removed |
Completion
as observed on 5 March 2014 |
140226_02 |
26-Feb-14 |
Open
burning activity should be prohibited ( Expo Drive East & Conventional
Avenue Junction) |
Opening
burning activities was ceased. |
Completion
as observed on 5 March 2014 |
8.0.6.
Five site inspections for Contract no.
HK/2009/02 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.5
Table 8.5 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
140213_01 |
13-Feb-14 |
Properly
measure should be provided for preventing filling material falling into the
sea ( TWCR4 ) |
A tarpaulin
sheeting was provided to prevent drop off. |
Completion
as observed on 19 Feb 2014 |
8.0.7.
Four site inspections for Contract no.
HK/2010/06 was carried out during this reporting period. No observation was
found in the reporting month.
8.0.8.
Four site inspection for Contract no.
HK/2012/08 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.7
Table 8.7 Summary of
Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
140218_01 |
18-Feb-14 |
The silt
curtain should be maintained properly to prevent dispersion of sediments. |
The silt
curtain was properly maintained. |
Completion
as observed on 25 Feb 2014. |
8.0.9.
Five site inspection for Contract no.
HY/2010/08 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.8
Table 8.8 Summary of Environmental
Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
140206_01 |
6-Feb-14 |
Provide
wheel washing combined with cleaning of public road if necessary (Victoria
Park Road) |
No further
silt trail was observed at exit and wheel washing is provided |
Completion
as observed on 14 Feb 2014 |
140227_01 |
27-Feb-14 |
Material
should be avoid placing near tree roots area |
Material
have been removed¡@ |
Completion
as observed on 6 March 2014¡@ |
9.0.1.
No environmental complaints were
received in the reporting period.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
February 2014 |
0 |
Sep 2010 ¡V Jan 2014 |
27 |
Total |
27 |
Table 9.2 Cumulative Statistics on
Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table
10.1 Summary of Key Construction Activities of Individual Contract(s)
to be commenced in Coming Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/15 |
¡P
Tunnel construction at TS2, TS4 & TPCWAE ¡P
Dismantling of struts at TS4 & TPCWAE ¡P
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal. ¡P
Mined tunnel lining construction |
¡P
Dust control during dust generating activities ¡P
Noise control measures shall be provided during restricted hours ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea |
HY/2009/18 |
¡P
Excavation of trial pit ¡P
Drainage works ¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction, extract
sheet pile, waterproofing and backfill ¡P
Trough structure construction and associated drilling and grouting ¡P
Road works ¡P
Bridges construction |
¡P
Noise level shall be controlled by reducing the breaking operation
rate. ¡P
Dust control during dust generating activities ¡P
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. ¡P
Appropriate plants and measures should be taken to ensure adequate
protections are provided for trees being transplanted. |
HY2009/19 |
¡P
Road works at Watson Road ¡P
Bored piling (Land) ¡P
Removal of strut at ELS ¡P
Construction of Pile cap, column and cross-head (Land) ¡P
Removal of marine platform ¡P
Construction of Dolphin Cap ¡P
ELS, EVB and Cut & Cover Tunnel ¡P
Installation of dewatering well ¡P
Laying of 1500f pipe ¡P
Launching of segments ¡P
Extraction of temporary pile from marine section ¡P
Construction of bridge TA1 ¡P
Pre-bored H-pile for Admin. Building |
¡P
Noise level shall be controlled by reducing the breaking operation
rate. ¡P
Noise barrier shall be implemented ¡P
Dust control during dust generating works ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. |
HK2009/01 |
¡P
Preparation works for the new temporary road at Expo Drive East ¡P
Temporary utilities diversion at the new reclaimed area ¡P
Installation of pre-bored H-piles at 4th row & ED (total 38 nos.
piles) ¡P
Remaining D-wall construction at tunnel south (13 nos. panels) ¡P
Excavation for stage 1 down to -10 mPD ¡P
Tunnel structure works ¡P
Base slab construction at Bay 5. |
¡P
Noise level shall be controlled by reducing no. of plants working in
parallel. ¡P
Well maintained enclosures for grouting mixing plants. ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ¡P
Dust control during dust generating works |
HK/2009/02 |
¡P
Complete all tunnel structure. ¡P
Pre-grouting and guide wall at TWCR4 area. ¡P
Bored pile construction those in the vicinity of Bridge 1 & 2
under Hung Hing Road Flyover Diversion (Stage 2) and continue others bored
pile construction at Tunnel Portion 3 & 4. ¡P
Mini-piling works for foundation of Bridge 3 under Hung Hing Road
Flyover Diversion (Stage 2) and complete mini-pile loading test at pile no.
M ¡P
Concrete deck and steel deck on existing Box Culvert O Bay 17 ¡V Bay
19. ¡P
Mobilization for D-Wall construction at Tunnel Portion 3 & 4 and
complete the preparation works for D-wall construction at Panel Nos. C ¡P
Existing ¡P
D-wall construction along Hung Hing Road slow lane. ¡P
D-wall construction at Tunnel Portion 6. |
¡P
Dust control during dust generating works ¡P
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HK/2010/06 |
¡P
Repair and installation of slotted panels ¡P
Installation of protection layer for precast unit |
¡P
Dust control during dust generating works. |
HK/2012/08 |
¡P
Site preparation works ¡P
Site survey |
¡P
Dust control during dust generating works |
HY/2010/08 |
¡P
Tree & root pruning works ¡P
Tree removal works, ¡P
Tree transplanting works, ¡P
Tree works within off-site nursery compound, ¡P
Drainage improvement works, ¡P
Sheet piling works, ¡P
Demarcation of graphics, ¡P
Pipe pile & pre-boring works, ¡P
Re-provisional of turtle pond, ¡P
Loop detector installation works & ¡P
UMP installation works. |
¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system. ¡P
Appropriate plants and measures should be taken to ensure adequate
protections are provided for trees being transplanted and retained on site. |
10.0.3.
The construction works of Contract no.
04/HY/2006 ¡V Reconstruction of Bus Terminus near
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.